将成本粗略估算、RFQ 和非合约成本来源列添加到预算视图

目标

将成本 ROM(粗略估算)、RFQ(报价请求)和 NCC(非合约成本)列作为源列添加到预算视图。

背景

如果贵公司选择使用项目变更事件工具,你可以使用以下步骤将一个或多个与变更事件工具关联的数据列添加到项目预算视图中。

变更事件数据列包括:

  • 成本 ROM。成本粗略估算的简称。此列显示变更事件的成本 ROM 估算。
  • RFQ。Request for Quote(报价请求)的简称。此列显示 RFQ 编号。
  • NCC。非合约成本的简称。此列显示未包含采购订单或分包合同明细项的成本值。
     注意
    如果你还想在预算视图中包含“营收 ROM”列,请参阅将变更事件列添加到预算视图

需要考虑的事项

先决条件

步骤

第 1 步:选择预算视图

添加本文中详述的列时,你有以下选择:

为你的预算视图选择首选选项后,使用下面详述的步骤添加所有推荐列。

第 2 步:添加推荐列

  1. 添加成本 ROM 列
  2. 添加成本 RFQ 列
  3. 添加非合约成本列
  4. 更新待处理成本变更列
  5. 更新预计成本列

添加成本 ROM 列

This adds a source column named 'Cost ROM' which shows a ROM estimate for change events. The value that appears in this column on a budget line item is not yet associated with a CCO, an RFQ, or a Non-Commitment Cost

Steps from the Configure Columns window in the Company Admin tool… Settings
  1. Click Create Source Column.
  2. Under New Source Column, do the following:
    • Column Name. Enter the name: Cost ROM
    • Column Source. Select Change Events
  3. Mark the ROM (Rough Order of Magnitude) checkbox to apply these filters: 
    1. Under Prime PCO, remove all of the marks from these checkboxes. 
    2. Under RFQ or Commitment Cost, mark the Without Cost checkbox only.
       Note
      This ensures that the source column includes only items that do not have associated costs, which excludes amounts from:
      • Request for Quotes (RFQs)
      • 2-tier Commitment Potential Change Orders (Commitment PCOs)
      • 1-tier Commitment Change Orders (CCOs)
    3. Under Non-Commitment Cost, mark the Without Cost checkbox only.
       Note
      This ensures that the source column includes only amounts with commitment costs and excludes Non-Commitment Costs (NCCs). 
    4. Under Scope, mark these checkboxes only:
      • In Scope
      • TBD
    5. Under Change Event Status, mark these boxes only:
      • Open
      • Closed
      • Pending
         Note
        • When filtering the columns data by change event status, any statuses not considered 'Void' are selected by default. 
        • If your company created custom statuses, those will NOT be shown by name. However,  any custom status considered 'Open', 'Closed', and 'Pending' are also selected by default. 
        • To learn more about custom statuses, see Set the Default Change Management Configurations.
  4. Click Create.
clipboard_e86165c22905ad693eba1df48da411279.png

添加成本 RFQ 列

This adds a source column named 'Cost RFQ' which shows costs associated with RFQs. The value that appears in this column on a budget line item is not yet associated with a CCO or a Non-Commitment Cost

Steps from the Configure Columns window in the Company Admin tool… Settings
  1. Click Create Source Column.
  2. Under New Source Column, do the following:
    • Column Name. Enter the name: Cost RFQ
    • Column Source. Select Change Events
  3. Mark the RFQ (Request for Quote) checkbox to apply these filters: 
    1. Under Prime PCO, remove all of the marks from these checkboxes. 
    2. Under RFQ or Commitment Cost, mark the Without Cost checkbox only.
       Note
      This ensures that the source column only includes values that do not have costs. This setting excludes amounts from:
      • 2-tier Commitment Potential Change Orders (Commitment PCOs)
      • 3-tier Commitment Potential Change Orders (Commitment PCOs)
      • 1-tier Commitment Change Orders (CCOs)
    3. Under Non-Commitment Cost, mark the Without Cost checkbox only.
       Note
      This ensures that the source column includes only amounts with commitment costs and excludes Non-Commitment Costs (NCCs). 
    4. Under Scope, mark these checkboxes only:
      • In Scope
      • TBD
    5. Under Change Event Status, mark these boxes only:
      • Open
      • Closed
      • Pending
         Note
        • When filtering the columns data by change event status, any statuses not considered 'Void' are selected by default. 
        • If your company created custom statuses, those will NOT be shown by name. However,  any custom status considered 'Open', 'Closed', and 'Pending' are also selected by default. 
        • To learn more about custom statuses, see Set the Default Change Management Configurations.
    6. Under RFQ Status, remove all of the marks from these checkboxes. 
  4. Click Create.
bv-column-cost-rfq.png

添加非合约成本列

This adds a source column named 'Non-Commitment Cost' column. The value that appears in this column on a budget line item represents a Non-Commitment Cost

 Important

If you plan to use the 'Non-Commitment Cost' column in the calculation for the 'Projected Cost' column (or for a 'Forecast' column), it is important to choose one (1) of the following options to ensure the calculation is NOT double-counted when related direct costs impact your budget:

  • Optional: Update the 'Cost RFQ' column to exclude 'Closed' change event statuses. Then instruct users who create relevant direct costs to also change the appropriate change event's status to 'Closed.' This will exclude the Non-Commitment Cost from the column's value. 
    OR
  • Optional: When users create relevant direct costs, instruct your users to delete the 'Non-Commitment Cost' from the appropriate change event. 
    OR
  • Optional: Do NOT create direct costs for the 'Non-Commitment Costs' being tracked in your budget.
Steps from the Configure Columns window in the Company Admin tool… Settings
  1. Click Create Source Column.
  2. Under New Source Column, do the following:
    • Column Name. Enter the name: NCC
    • Column Source. Select Change Events
  3. Select the RFQ (Request for Quote) checkbox to apply these filters: 
    1. Under Prime PCO, remove all of the marks from these checkboxes. 
    2. Under Scope, mark these checkboxes only:
      • In Scope
      • TBD
    3. Under Change Event Status, mark these boxes only:
      • Open
      • Closed
      • Pending
         Note
        • When filtering the columns data by change event status, any statuses not considered 'Void' are selected by default. 
        • If your company created custom statuses, those will NOT be shown by name. However,  any custom status considered 'Open', 'Closed', and 'Pending' are also selected by default. 
        • To learn more about custom statuses, see Set the Default Change Management Configurations.
    4. Under Non-Commitment Costs, mark the Without Costs checkbox.  
  4. Click Create.
bv-column-ncc.png

更新待处理成本变更列

The Procore Standard Budget View includes a 'Pending Cost Changes' source column. Use the steps below to update that column.  

Steps from the Configure Columns window in the Company Admin tool… Settings
  1. Under Source, highlight the 'Pending Cost Changes' column.
  2. Click Edit.
  3. Ensure the Column Source is set to Commitments.
  4. Under Subcontracts, mark the Draft checkbox and remove the marks from all other checkboxes.
  5. Under Purchase Order Contracts, mark the Draft checkbox and remove the marks from all other checkboxes.
  6. Under Change Orders, mark the Draft checkbox and remove the marks from all other checkboxes. 
  7. Click Update.
bv-column-pending-cost-changes.png

更新预计成本列

The Procore Standard Budget View includes a 'Projected Cost ' calculated column. Use the steps below to update that column.  

Steps from the Configure Columns window in the Company Admin tool… Settings
  1. Under Calculated, highlight the 'Projected Costs' column.
  2. Click Edit.
  3. Configure the calculation's drop-down lists as follows:
    • Select the 'Cost ROM' column. 
    • Select the plus (+) sign.
    • Select the 'Cost RFQ' column. 
    • Select the plus (+) sign.
    • Select the 'NCC' column.  
  4. Click Update.
bv-column-projected-costs.png

 

If you would like to learn more about Procore's change events management software and how it can help your business, please visit our construction change order product page icon-external-link.png.