使用项目送审工具为项目创建送审。
在建筑行业,送审材料是指分包商向总承包商提供的书面和/或物理信息。然后在将设备、材料等制造并交付给项目之前,需要将这些信息提交给设计团队进行审批。送审材料可以采用各种格式,例如施工图纸、设备分页图和材料样品。建筑师和工程师之所以需要送审材料,主要是为了验证是否按照设计文件/合同文件的规定在项目中安装正确的产品和数量。
In Procore, a submittal manager is a person responsible for overseeing a submittal throughout its lifecycle. If you create a submittal and have 'Standard' or 'Admin' level permission to the Submittals tool, your name appears as the 'Submittal Manager' by default. However, users with 'Admin' level permission to the Submittals tool have the ability to assign the submittal manager role to any Procore user who has been granted 'Standard' or 'Admin' level permission to the Submittals tool (Note: Users with 'Standard' permission do not have permission to change the submittal manager). The 'Submittal Manager' field lets you change ownership of a submittal when the person who created a submittal (or that submittal's current manager) is no longer a member of the project team.
尽管每个公司和项目都可能有其特定的流程,但项目经理或工程师通常会担任送审 经理。 首先,送审 经理将创建送审。 接下来,分包商提供送审所需的文档。 然后,所需的文件准备就绪后,送审将发送给相应的设计团队成员以供审核和批准。
|
|
对送审工具具有标准权限的用户在创建新送审时只能查看以下字段:
标题、规范分项、编号和修订、送审类型、责任承包商、接收自、最终截止日期、地点、关联图纸、通讯名单、后续行动者、私密、描述、附件
Title. The descriptive name that best summarizes the information in the submittal.
Spec Section. Denotes the corresponding section from the project's specifications book. See Where do the selections in the 'Specification Sections' drop-down list in the Submittals tool come from?
Number & Revision. The submittal number and its revision number. See How are submittals numbered in Procore?
Submittal Package. The submittal package that contains the submittal. In Procore, adding submittals to a package is optional. The decision to add submittals to a submittal package is based on your project's requirements, which is determined by your company's or project's management team. For instructions, see Create a Submittal Package.
Status. The current status of the submittal. Only a user with 'Admin' level permission to the Submittals tool can change a submittal's status. See What are the default submittal statuses in Procore? and What is a 'Draft' Submittal?
注意事项:
如果送审是未完成且没有工作流,则后续行动者是送审经理,该项应显示在他们的"我的未完成项"工具中。
如果送审为未完成并且确实有工作流,则当前工作流步骤任务任务分配 对象有后续行动者。工作流完成后,BIC 将返回给送审经理。
如果送审为已关闭,则后续行动者将被清除。
Responsible Contractor. The company name of the contractor/subcontractor that is responsible for completing the work specified on the submittal.
Received From. The contact for the responsible contractor who provided the submittal information to the project team.
Submit By. Select the date by which a contractor/subcontractor must submit all relevant documentation (i.e., documents, drawings, manuals, plans, and so on) for the submittal to the project's design team for review.
Issue Date. The date the contractor/subcontractor submitted the submittal items (i.e., documents, plans, and so on) to your project team for the review process.
Received Date. The date that the submittal information was received from the contractor/subcontractor responsible for the performing work associated with the submittal.
Final Due Date. The due date by which all approvers on the submittal workflow must submit a response.
Lead Time. The expected number of calendar days that will be required for the material/services for the submittal to arrive.
Required On-Site Date. The date by which materials related to the work detailed on the submittal must be delivered and available at the construction site.
Cost Code. The cost code for the submittal. Cost codes are managed in the 'Cost Code' segment in Procore's Work Breakdown Structure.
Submittal Manager. The name of the submittal manager. This is the person who is responsible for overseeing the submittal throughout its lifecycle in Procore. Each submittal can have a different submittal manager or your project team can configure a 'Default Submittal Manager' for all of your submittals. See What is the 'Submittal Manager' role?
Type. The information type associated with the submittal. The default type selections in Procore include: Document, Pay Request, Payroll, Plans, Prints, Product Information, Product Manual, Sample, Shop Drawing, Specification, and Other. See Create Custom Submittal Types.
Private. Indicates privacy settings for the submittal. When a submittal is marked 'Private', it is only visible to users with 'Admin' level permissions on the Submittals tool, users in the Submittal Workflow, and members of the submittal's Distribution List. Users with the 'View Private Submittals Associated to Users within Same Company' granular permission enabled on their permissions template can also view a submittal marked 'Private' if another user in their company is associated with the submittal. See Mark a Submittal as Private.
Location. The location at the job site for the submittal. This can be an existing location from the Location list or a tiered location. See Add Tiered Locations to a Project.
Linked Drawings. Renderings stored in the project's Drawings tool that are linked to the submittal. See Link Related Items on a Drawing.
Description. Informative details, notes, and/or actions that describe the submittal.
Attachments. Attach any relevant files. You have these options:
Distribution List. The people who will receive email notifications from Procore as the submittal progresses through the submittal workflow. If your project team has created any distribution lists in the Project Directory, you can select those lists here. See Add a Distribution Group to the Procore Directory).
送审进度计划计算是可以启用的可选功能。请参阅启用送审进度计划计算。启用后,送审工具将分析“物料要求送抵现场日”、“前置时间”、“设计团队审核时间”和“内部审核时间”字段中的条目,为送审者和审批者提供有关送审工作流“截止日期”的建议。还会自动填充“计划返回日期”、“计划内部审核完成日期”和“计划提交截止日期”字段。
Design Team Review Time. The number of days allotted for the design team's review on the submittal.
Lead Time. The expected number of calendar days that will be required for the material/services for the submittal to arrive.
Required On-Site Date. The date by which materials related to the work detailed on the submittal must be delivered and available at the construction site.
Internal Review Time. The number of calendar days that your project's design team requires to ensure the submittal is properly reviewed.

拥有项目送审工具“管理员”级别权限的用户可以创建一 (1) 个或多个送审流程模板,然后可以在首次创建时将其添加到新送审中。这可以防止每次创建送审时都必须添加新的送审工作流,从而节省了数据输入时间。


完成上述步骤后,选择以下选项之一: