设置和使用送审进度计划计算以自动计算审批者答复的日期建议。
送审进度计划计算是一种可选配置功能,可启用此功能以便与项目级别送审工具一起使用。在 Procore 项目上启用时,此选项会分析以下关键日期,这些日期由创建者在送审汇总包或送审项中的“送审进度计划信息”下输入:
分析日期条目后,Procore 会自动在以下字段中为最终用户填充计算出的日期值:
根据上面计算出的日期值,Procore 还会建议以下字段的日期:
这有助于送审创作者确保提交给审核团队的送审汇总包和项按时获批。
Design Team Review Time. The number of days allotted for the design team's review on the submittal.
Lead Time. The expected number of calendar days that will be required for the material/services for the submittal to arrive.
Required On-Site Date. The date by which materials related to the work detailed on the submittal must be delivered and available at the construction site.
Internal Review Time. The number of calendar days that your project's design team requires to ensure the submittal is properly reviewed.