Milestone Dependencies allow you to establish a relationship between two milestones so that you can track and maintain project schedules more efficiently. For example, a 'Construction Start' milestone can be dependent on the date for the 'Drawings Complete' milestone. If the forecast date for 'Drawings Complete' is adjusted by 10 days, the forecast date for 'Construction Start' will also adjust by 10 days.
Notes:
- 你不能为列出的第一个里程碑设置依赖项,因为之前没有任何内容。
- 你只能在手动添加新里程碑时设置里程碑依赖项,而不是从模板添加。